At Troitskaya GRES completed the installation of steam turbine condenser CLN-660-24.2/566/566. Capacitor my body was established by the spring supports and cemented into the Foundation of the base plate.
The capacitor is one of the key elements of turbine installations. It provides the heat from the thermodynamic cycle of steam power unit.
In the near future, the final stage of the installation itself steam turbine.
*OJSC «QUARTZ-New Technologies» - one of the leading Russian engineering companies. In 2013 commercial launch of 270 MW power (CHP-90 Omsk CHPP-3, PGU-180 Джубгинка TPP). In 2014 OJSC «QUARTZ-New Technologies» plans to complete the construction of one of the largest coal-fired power units with a capacity of 660 MW at the Troitskaya TPP. Over the last five years the company has completed four major projects in the energy industry, increasing the energy potential of regions of its presence on the 900 MW.